Revised Program

The timetable for the regeneration of the Sherwood Close Estate has been revised to provide additional time to re-house residents in phase one of the development. This revised timetable means that certain key dates within the programme including planning submission and start-on-site need to be moved to a later date. The planning application submission date has been revised to Spring 2014 and we expect to have a decision by the Autumn to allow a start on site to take place later in 2014.

Phase 1 – Archer House, 1-10, 12-21 and 70-72 Sherwood Close – We are now looking to achieve vacant possession of Phase 1 in March 2014. We have allowed a period of approximately 6-7 months between vacant possession and start on site to allow us to carry out pre-demolition site investigation work. We anticipate phase 1 construction to start late 2014 and expect the construction period to end Spring 2016.

Phase 2Crossbow House, 22-37, 39-42 & 43-68 Sherwood Close – The decanting of phase 2 will end late January 2016 before construction starts on site early March 2016. The new homes are expected to be available in Autumn 2017.

Phase 3Target House – The decanting of phase 3 will end late July 2017 before construction starts on site early September 2017. The new homes are expected to be available in Spring of 2019.

A summary of the key dates are:

Phase 1   Vacant possession date

March 2014

  Construction start-on-site

November 2014

  Phase 1 complete

February 2016

 

Phase 2   Vacant possession date

January 2016

  Construction start-on-site

March 2016

  Phase 2 complete

Autumn 2017

 

Phase 3   Vacant possession

July 2017

  Construction start-on-site

September 2017

  Phase 3 complete

Spring 2019